COVERAGES-SPECIFIC.
The specific coverage's as delineated in the warranty contract are
outlined below:
Equipment:
Manufacturer:
BAE Systems
CAGE:
ODODO
NSN:
5895-01-518-8783
Part Number:
P320A002-03
Contract:
DAAB07-01-C-B014
The items covered by this warranty are the CV-3338B/ASN-128D Signal Data Converter (SDC)
and the SRAs. The SDC units are under warranty for a period of five (5) years beginning on the
date of acceptance by the government. The specific warranty is that, notwithstanding
inspection and acceptance by the government of equipment furnished under this contract or any
provision of this contract concerning the conclusiveness thereof, and subject to the
qualifications herein, the contractor guarantees that equipment delivered under this contract and
each component thereof called for by the terms and conditions of this contract and any
amendments thereto:
a.
are produced so as to conform to all designs and manufacturing requirements and
shall operate in their intended environment IAW specifications and/or drawings.
b.
are free from defects in material, and workmanship which would cause the supplies
to fail to conform to the specified performance requirements of the contract.
c.
shall operate in the intended environment IAW specifications and/or drawings.
COVERAGE EXCLUSIONS.
a.
The contractor shall not be responsible under this warranty clause for the correction
of defects in resulting from Government-furnished property.
b.
The Contractor shall not be obligated to repair or replace supplies under the
provisions of this warranty clause if loss or damage occurs by reason of SDC
induced fire, explosion, or aircraft crash; acts of God such as flood, hurricane,
tornado, and earthquake; or combat damage.
c.
The Contractor shall not be obligated under this warranty to: repair or replace
supplies rendered inoperable by unauthorized maintenance by Government
personnel (authorized maintenance is defined in the respective Technical Manuals);
repair external physical damage caused by accidental or willful mistreatment by
noncontractual personnel (while outside of the Contractor's facilities and control
responsibility); repair internal damage which, in the determination of the
Government Contracting Officer was caused by accompanying external damage as